Kitchen Remodel Budget Breakdown: Real Line Items From 3 Kitchens in NH, VT & ME (2027)

Kitchen remodel cost · NH, VT & ME · 2027

Kitchen Remodel Budget Breakdown: Real Line Items From 3 Kitchens in NH, VT & ME (2027)

How much does a kitchen remodel cost in New England? Three real budgets from my contractor days, every line item, markup included.

Purple kitchen remodel in Vermont with custom painted cabinets, a curved island with white stone counters, blue glass pendants and a wood range hood
The nice kitchen: custom cabinets, a curved island and a built-in range alcove. Cabinetry and photo by Crown Point Cabinetry.

The short version

How much does a kitchen remodel cost in New England? Here are three real kitchen budgets from my contractor days, cheapest to nicest:

The bare-bones kitchen$83k

Full gut, Home Depot cabinets, Vermont, 2025. $73,699 on paper, then a structural beam, gas and electrical work, and a backsplash got added.

The basic template$101,539

My starting estimate for every kitchen, all Tier 1, kept current through early 2026.

The nice kitchen$217,707

Vermont, 2025. Custom cabinets, a panel-ready fridge, a built-in range alcove, a bar sink. Nice, not nuts.

What they all have in common:

  • Cabinets and counters are the biggest chunk. 39% of the cheap one, 66% of the nice one.
  • Markup was 30% on most stuff, 20% on custom cabinets and 0% on labor. On the $218k kitchen, the company kept $38k, 17.5% of the price. That covered design, running the job, overhead and profit.
  • Change orders happen. Beams, subfloors, electrical panels. Nobody knows until the walls come open.

If you just wanted the numbers, there they are. If you want to see every damn line, keep scrolling.

Where these numbers came from

Before Bienvenue & Co., I was the designer and COO at a design-build company in NH and VT. I built our estimates in Buildertrend, and I'm pulling three of them out for you. Client names and addresses are gone.

  • The bare-bones job: a Vermont kitchen, approved fall 2025, part of a whole-house project. Full gut, new layout, cabinets priced on Home Depot's unfinished stock line.
  • The template: the starting estimate I'd use for every kitchen, set to Tier 1, the basic level. I kept it updated through early 2026, so it's close to today's prices.
  • The nice job: a Vermont kitchen, approved spring 2025. Full gut, new layout, about 60 feet of custom cabinets, existing wood floors refinished.
  • What clients saw: every line item and a total for each section. Not the cost of each line, and not the markup. You're getting both.
  • Design: we didn't charge for it separately. The markup covered it. (More on that below.)

And even this granular, we'd still forget stuff. Usually small plumbing parts, like drains, supply lines and elbows. Nobody thinks about them, and plumbing confuses even people in the industry. When we forgot something, we ate the cost. That's the deal with a fixed price: the contractor's mistakes are on them, not you.

The common ways contractors price a remodel, so you know what you're looking at:

  • One fixed price. A total for the whole job, based on their experience with similar projects. Simple to read, hard to compare.
  • Fixed price with sections. What you're seeing here: a total per section, with allowances for the stuff you haven't picked yet.
  • Cost plus. You pay what it actually costs, plus a percentage or a set fee on top. Transparent, but the final number isn't locked in.
  • Time and materials. Hourly labor plus materials. Common for small jobs and repairs, rare for a full kitchen.

None of these is the "right" one. Ask which one your contractor uses and what happens when something gets missed.

White kitchen remodel with a navy island, farmhouse sink under two windows, panel-ready refrigerator and exposed ceiling beams
Another kitchen of mine: a navy island, a farmhouse sink and a panel-ready fridge.

Where the money goes in a kitchen remodel

Cabinets and counters are the biggest chunk every time. The nicer the kitchen, the bigger that chunk gets.

SectionBare-bones jobBasic templateNice job
Cabinets + counters$28,860 (39%)$47,037 (46%)$144,243 (66%)
Appliances$7,320 (10%)$14,294 (14%)$45,159 (21%)
Floors$14,667 new tile (20%)$12,457 new tile (12%)$4,500 refinished (2%)
Walls: drywall, paint, trim$12,216 (17%)$12,218 (12%)$8,788 (4%)
Electrical + plumbing$7,870 (11%)$7,090 (7%)$6,130 (3%)
Sinks + faucets$1,985 (3%)$2,505 (2.5%)$4,637 (2%), two sinks
Job site: demo, dumpster, clean-upbilled with the rest of the house$4,249 (4%)$4,249 (2%)
Lighting$780 (1%)$1,690 (1.7%)not in the estimate
Total$73,699$101,539$217,707

Look at the walls and floors. Drywall, paint and tile cost about the same no matter how fancy the kitchen is. That's why a cheap kitchen can't get much cheaper.

So when someone says "we'll save money by going cheap on the faucet," the faucet on the $218k job was $538. If you want to move the number, cabinets, counters, layout and appliances are where it moves.

Custom range alcove with a wood-clad hood, green tile backsplash and induction cooktop between purple cabinets
The $16,250 custom range alcove from the line items below. Cabinetry and photo by Crown Point Cabinetry.

Kitchen remodel cost breakdown, line by line

Here's the whole damn thing from the nice kitchen: what the company paid, the markup, and what the client paid. Clients only ever saw the section totals. Scroll past if you don't care.

ItemBuilder costMarkupClient price
Cabinets + counters$118,833.98$144,243.38
Custom cabinets$80,686.4820%$96,823.78
Countertops$28,000.0030%$36,400.00
Cabinets install$6,000.000%$6,000.00
Cabinet hardware (58)$2,610.0030%$3,393.00
Cabinet hardware install$640.500%$640.50
Crown molding install$600.000%$600.00
Appliance pulls (3)$297.0030%$386.10
Appliances$35,206.00$45,159.40
Custom range alcove (incl. tile)$12,500.0030%$16,250.00
Panel-ready refrigerator$8,530.0030%$11,089.00
Single wall oven$5,399.0030%$7,018.70
Induction cooktop$3,499.0030%$4,548.70
Undercounter beverage cooler$3,250.0030%$4,225.00
Refrigerator + freezer install$672.000%$672.00
Cooktop install$500.000%$500.00
Microwave install$252.000%$252.00
Dishwasher install$252.000%$252.00
Oven install$252.000%$252.00
Beverage cooler install$100.000%$100.00
Electrical, plumbing + floors$9,880.00$10,630.00
Refinish existing wood floors (300 sf)$4,500.000%$4,500.00
Electrical subcontractor$2,500.0030%$3,250.00
Plumbing rough-in labor$2,880.000%$2,880.00
Walls$8,277.24$8,788.12
Baseboard + casing labor$2,500.000%$2,500.00
Wall paint labor$1,649.480%$1,649.48
Sheetrock labor$1,440.000%$1,440.00
Primer labor$984.800%$984.80
Baseboard trim$748.0030%$972.40
Interior primer$454.0030%$590.20
Sheetrock$435.0030%$565.50
Spackle (green)$21.9030%$28.47
Spackle (blue)$21.9030%$28.47
Mesh tape$15.1830%$19.73
Painter's tape$6.9830%$9.07
Sinks + faucets$3,732.91$4,636.79
Kitchen sink$1,558.0030%$2,025.40
Bar sink$668.0030%$868.40
Kitchen faucet$414.1930%$538.45
Bar faucet$372.7230%$484.54
Sink install (2)$480.000%$480.00
Faucet install (2)$240.000%$240.00
Job site$3,670.00$4,249.00
End-of-job clean-up$720.0030%$936.00
Trash station$710.0030%$923.00
Material pick-up$720.000%$720.00
Demo + prep$720.000%$720.00
Dump trailer$500.0030%$650.00
Porta potty$300.000%$300.00
Total$179,600.13$217,706.69

Yes, spackle gets its own line. That's what I mean by granular.

The estimate was a guess, and that's normal

That estimate was written before the design was done. At that point, the contractor is guessing: experience, a conversation with you, and a template. That's all they've got. And this was a detailed guess. Plenty of estimates are a lot rougher.

Here's what changed once we designed it:

  • We added a separate panel-ready freezer. It isn't even in the estimate above.
  • The cabinets went up. She wanted all the bells and whistles, and she was happy to pay for them.
  • I splurged where she'd use it every day and saved in other places to pay for it.
Panel-ready refrigerator and freezer hidden behind purple custom cabinet doors next to a drawer microwaveUndercounter beverage cooler under purple glass-front cabinets between two windows
The panel-ready fridge and freezer, and the beverage cooler with glass uppers. Cabinetry and photo by Crown Point Cabinetry.

She cooks from scratch for a big, busy household, way more than most people. Those choices made sense for her. They might not for you.

The point: a price before design is a ballpark. A price after design, with every selection made, is a real number. That's the whole reason design comes first.

Contractor markup: is 30% normal? Yes.

On the nice kitchen, the company paid $179,600 and charged $217,707. The difference, $38,107, is 17.5% of the price. That's not profit. That's everything that isn't materials and labor.

And the kitchen alone took three to four months. (The whole job ran six, with an addition, laundry room and powder bath built at the same time.) $38k over three or four months is about $9,500 to $12,700 a month, for a whole company, before it pays for insurance, the truck, the office or the people running the job (including the designer). Sounds like a lot until you break it down. It's really not crazy.

How the markup was set:

  • 30% on materials, appliances and subs. Tile, paint, sinks, the electrician, the fridge.
  • 20% on the custom cabinets. The cabinets were so expensive that I didn't want to hit her with full markup on top. Even at 20%, that one line covered all my design time.
  • 0% on labor lines. That doesn't mean labor was at cost. Every labor rate was set to cover overhead: equipment, insurance, all of it. That's why a master plumber bills $120 an hour.

And quick math lesson: 30% markup is not 30% profit. Mark something up 30% and the company keeps 23% of the price, before paying for anything below.

What that $38k paid for:

  • Design. We didn't charge a separate design fee. This was it.
  • Insurance. Liability and workers' comp, so you're not on the hook when someone gets hurt in your kitchen.
  • The warranty. A year of callbacks after final payment.
  • Running the job. Scheduling subs, ordering, chasing back-ordered stuff, answering your texts.
  • Buying everything. The contractor buys all of it, appliances too, and pulls the permits. If something shows up broken, it's their problem, not yours.
  • Keeping the lights on. The office, the truck, the tools, the software, the people.

A contractor with no markup is either lying or going out of business. Neither one should be in your house for three months.

What wasn't in the $101k

These were listed as add-ons, priced separately. A lot of people assume half of these come standard. They don't.

Add-onAbout
Panel-ready appliances+$2,000 to $15,000 each
Slab backsplash (same as counters)+$4,000
Built-in espresso machine+$3,500
Double oven+$3,200
Built-in coffee maker+$3,125
Custom range hood cover+$3,000
Pot filler+$2,000
Undercounter beverage cooler+$2,000
Tile backsplash+$1,500
Trash compactor+$1,250
Under-cabinet lighting+$1,200
Instant hot water+$600
Garbage disposal+$450

Add a tile backsplash, under-cabinet lights, a pot filler and a hood cover, which is pretty much what everyone saves on Pinterest, and you're at about $109k. Still Tier 1 everything else.

Also not in there: whatever's hiding in your walls. Rot, weird plumbing, ancient wiring, code upgrades. Contractors build in a cushion for that, and you should too.

Tier 1 vs. Tier 2 vs. Tier 3

That $101k was Tier 1 on everything. Here's what each tier actually means, and what the stuff costs at each one.

  • Tier 1: basic shapes, limited finishes. Home Depot, Lowe's, Wayfair, Build.com.
  • Tier 2: more shapes and finishes. Think West Elm, Pottery Barn, Kohler.
  • Tier 3: no limits. Specialty, custom-built and handmade. Think Rejuvenation, Perigold.
ItemTier 1Tier 2Tier 3
Cabinetry (per box)$300 to $900$900 to $1,500$1,500 to $8,000+
Countertops (per sq ft)$120 to $150$150 to $250$250 to $350+
Cabinet hardware (each)$10 to $20$20 to $50$50 to $100+
Backsplash tile (per sq ft)$12 to $25$25 to $65$65 to $200+
36" fridge$2,000 to $3,300$3,300 to $6,000$6,000 to $10,000+
Panel-ready fridge$10,000 to $13,000$13,000 to $20,000$20,000+
Gas range$1,000 to $3,500$3,500 to $12,000$12,000 to $45,000+
Induction range$2,200 to $4,500$4,500 to $15,000$15,000 to $55,000+
Dishwasher$800 to $1,200$1,200 to $1,800$1,800 to $3,500+
Drawer microwave$1,600 to $2,000$2,000 to $2,500$2,500+
Wall-mount hood$700 to $1,000$1,000 to $3,000$3,000 to $10,000+
Kitchen sink$500 to $900$900 to $2,000$2,000 to $5,000+
Kitchen faucet$750 to $1,500$1,500 to $2,500$2,500 to $6,000
Pot filler$500 to $800$800 to $1,500$1,500 to $3,000
Under-cabinet lighting (per ft)$25 to $35$35 to $45$45 to $55
Pantry$2,000 to $6,000$6,000 to $12,000$12,000 to $30,000+

Material prices only, from my pricing guide (Dec 2025). Install is on top.

For a real-life version of the tiers, look back at the three kitchens. The bare-bones one was Tier 1 with Home Depot cabinets. The nice one had Tier 2 hardware, custom cabinets and a panel-ready fridge.

Teal kitchen cabinets with white counters, a window over the sink and a stainless range hood
Teal cabinets and white counters in another kitchen of mine.

Why kitchen remodels go over budget: change orders

Estimates are tidy. Real jobs aren't. Here's what got added to the kitchens after the price was signed.

Change orderJobPrice
Electrician, final balanceNice$9,505
New hardwood floor in the kitchenNice$9,450
ElectricalNice$6,195
Kitchen subfloor replacementNice$4,350
Living room lighting + one kitchen lightNice$4,030
Crown molding on the cabinetsNice$3,013
Electrical sub-panelNice$1,950
Backsplash at the sinkNice$1,240
Kitchen electrical + gasBare-bones$3,630
Kitchen structural beamBare-bones$3,551
Kitchen backsplashBare-bones$1,855
  • The nice kitchen picked up about $40k in kitchen change orders, plus more on the addition built at the same time. The whole project signed at $363k, change orders took it past $413k, and I think the final bill landed somewhere around $450k.
  • The bare-bones kitchen picked up about $9k, taking it from $73,699 to about $83k. Kitchen and bath rewiring added another $6,653 across both rooms.
  • Some of it was choices, like the backsplash, the crown and the new floor. Backsplash wasn't in either original price, which is normal. See the add-ons above.
  • Some of it was the house. A rotted subfloor, a beam, a whole electrical panel. Nobody knew until the walls came open.

That's the cushion I keep yelling about. Your contractor builds one in. Build your own on top.

Light wood kitchen remodel with a large white island, stainless range hood and appliances, and a window over the sink
Light wood cabinets, a big white island, nothing fussy.

How this compares to the $80k floor

I tell people a kitchen in NH, VT & ME starts at $80k. The cheapest full-gut kitchen here, with Home Depot cabinets, landed at about $83k. So yeah, the floor is the floor.

  • $80k is construction and materials only. Design isn't in it. At the design-build company, design was covered by the markup instead of a separate fee.
  • $80k means basic everything. Big-box brands, few choices, not much that makes it yours.
  • Most kitchens land higher, especially in older houses. Even a 1980s house has surprises.
  • Prices haven't gone down since these were priced.

Quick answers

How much does a kitchen remodel cost in New England?

For a full gut in New Hampshire, Vermont or Maine, plan on $80k at the absolute minimum. The three real kitchens here landed at about $83k, $101k and $218k.

Why do kitchen remodels go over budget?

Surprises behind the walls (rot, beams, old wiring), things added once the design is done, and items the estimate missed. On the nice kitchen here, change orders added about $40k.

What percent of a kitchen remodel is cabinets?

In these three kitchens, cabinets and counters were 39% to 66%. Nothing else came close.

Is 30% contractor markup normal?

Yes. On these jobs it was 30% on materials and subs and 20% on custom cabinets. It pays for insurance, the warranty, running the job and buying everything.

Do contractors mark up appliances?

Usually, yes. They buy them, store them, deal with the damaged ones and install them. That's work.

How much should I set aside for surprises?

Enough that a rotted beam doesn't end the project. Your contractor builds in a cushion. Build in your own on top.

Is $80k really the minimum for a kitchen in NH, VT & ME?

For a full gut with basic finishes, yes. Construction and materials only, no design.

So, can you actually do this?

Book a free intro call

Next
Next

Who Should I Hire to Design My Kitchen Renovation?